Exact 900 Sq Ft Pour Takeoff • 900 Sq Ft Square Metal Shop or 3-Car Garage

How Many Yards of Concrete for a 30x30 Slab? (2026 Cost & Rebar)

Direct Answer: A 30'×30' (900 sq ft) slab requires 12.22 cubic yards at 4" thick (11.11 raw + 10% waste) or 18.33 cubic yards at 6" thick for a shop or vehicle lift. Add +5.7 yd³ for a 12"×18" monolithic perimeter footing.

Customize Your 30' × 30' Pour

900 Sq Ft
Slab Concrete Thickness

4" = residential/patio • 5"–6" = shop bays, RV storage & 2-post car lifts.

Exact Ready-Mix Order for 30' × 30' (4" Thick)2 Ready-Mix Trucks (9.5 yd³ each)
17.9 Cubic Yards(16.3 raw + 10% waste)
Concrete Material
$3,047
@ $170/yd³
Turnkey Poured Est.
$8k–$12k
Labor, rebar & finish
#4 Rebar (16" OC)
81 Sticks
20-ft bars + 12% lap
4" Gravel Base
18 Tons
#57 crushed stone
Pour Breakdown: Flat 4" slab = 11.11 yd³ + 120 LF monolithic perimeter footing = 5.19 yd³. Mixing by hand would require 807 bags of 80-lb concrete mix—always order ready-mix transit trucks for a 30x30 structural slab.
30x30 Concrete Slab Thickness, Monolithic Footing & 2026 Cost Matrix
Slab ThicknessFlat Order (w/ 10% Waste)With 12"×18" Monolithic EdgeReady-Mix TrucksBest Application
4 Inches (3,500 PSI)12.22 yd³17.9 yd³2 truck(s)Residential living area, patio, light passenger cars
5 Inches (4,000 PSI)15.28 yd³21.0 yd³2 truck(s)Full-size 3/4-ton trucks, 2-post car lift (4.5"+ min)
6 Inches (4,000 PSI)18.33 yd³24.0 yd³2 truck(s)RV storage bays, tractors, heavy mechanic workshops
8 Inches (4,500 PSI)24.44 yd³30.1 yd³3 truck(s)Commercial fleet semi-trucks & heavy machinery

Frequently Asked Questions — 30x30 Concrete Slabs

How many cubic yards of concrete do I need for a 30x30 slab?

A 30' × 30' (900 sq ft) slab at 4 inches thick needs 11.11 raw cubic yards, or 12.22 cubic yards with a standard 10% waste buffer (2 ready-mix trucks). At 6 inches thick for a shop or vehicle lift, order 18.33 cubic yards.

How much does a 30x30 concrete slab cost in 2026?

Ready-mix concrete delivery alone for a 4-inch 30x30 slab costs roughly $1,894 to $2,261 ($155–$185/yd³). A full turnkey contractor-poured 4-inch slab with gravel base, vapor barrier, #4 rebar (81 sticks), forming, and finishing averages $6,210 to $9,360.

How much extra concrete does a monolithic thickened edge add to a 30x30 slab?

A standard 12"-wide × 18"-deep monolithic perimeter footing around the 120 linear feet of a 30x30 slab adds approximately 5.7 cubic yards (including 10% over-excavation buffer).